material availability check not being executed

Logistics : PS

Moderators: Snowy, thx4allthefish

material availability check not being executed

Postby YYZ_SAP » Fri Aug 15, 2014 6:24 am

First of all: I’m an SD consultant with limited knowledge about PS

At our current client are we facing an issue with the material availability check in project system orders, created through e.g. CJ20N. The client mentions, that the availability check on the components is not being executed and therefore is effecting their operations

I did check SAP OSS and found the following OSS notes:
01774744 Planning quantity of PIR is not getting updated properly
01745038 BAPI_NETWORK_COMP_CHANGE is updating PBED-PLNMG incorrectly
01774657 BAPI_NETWORK_COMP_CHANGE is not updating PBED-PLNMG –III
Those notes were also implemented

Did find transaction CJBN and did some testing, but did get the message
BL 001
Availability check not activated

I did check transaction
OPJJ and everything looks good.
OPJK and everything looks good

At this point I’m totally clueless on how to resolve the issue.

If you would have any suggestions, pointers or remarks: they would be appreciated.

Thanks and regards,
Jan Pel
YYZ_SAP
 
Posts: 1886
Joined: Thu May 08, 2003 11:44 am
Location: YYZ

Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 4 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.