How to separate Capex & Opex WBSs?

Logistics : PS

Moderators: Snowy, thx4allthefish

How to separate Capex & Opex WBSs?

Postby Bezladnova » Tue Jun 03, 2014 9:32 am

Hi Gurus,

Please can you knidly share how other companies differentiate between Capex & Opex WBSs?

We normally have some Capex & some Opex WBS under one Project Profile. So we need different validations & user input depending on if it is Capex or Opex WBS.

Ideally, we would have user just choosing between Capex or Opex option & all validations & diffrence in required input to follow.

Currently we use Field Keys for this & later refer to them in a validations. This has lots of disadvantages, so I wonder how other companies do it.


Thank you!
Bezladnova
 
Posts: 1
Joined: Thu Feb 27, 2014 7:03 am

Re: How to separate Capex & Opex WBSs?

Postby knowledgeWorx » Thu Jun 05, 2014 10:54 am

We have a fixed naming scheme, usually our WBS are named <project id>.x.12345 where x is either 1 or 7, indicating capex or opex. The structure is created from a project template, of course. However, I'm not sure if this solution is optimal either. Would also like to hear how others do it.
SAP Enthusiast, PM/PS/CS Consultant, Hobby Blogger.
http://www.dev-workbench.com
knowledgeWorx
 
Posts: 17
Joined: Mon May 05, 2014 9:36 am
Location: Germany


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 1 guest





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.