Postby Lee1706 » Fri Mar 21, 2014 5:52 am

I hope someone can help as I have a problem. One of our order types "ZSS1" shows commitments in PS whenever a WBS element is entered in the Location tab of a Service Order. However, no commitment appears in PS when a WBS element is entered in another Service Order type "ZSS3". Both order types were created before I started in this job.

Does anyone know where I define integration between the order type ZSS3 and PS so that when a WBS element is used it shows the commitment in PS. I cannot seem to find the config location in SPRO.

Thank you in advance.