Block dates (PROJ-PLFAZ/PLSEZ) in project definition

PostPosted: Thu Dec 19, 2013 4:32 am
by unurd
Hi,

Trying to block dates (PROJ-PLFAZ/PLSEZ) in project definition with authorization key in the status profile.

I mark these as forbidden but still the dates are open and not grey.
- Delete basic dates
- Schedule basic dates
- Set basic finish
- Set basic start

It works fine in WBS elements.

Any suggestions?

Thanks, Amos.