Error on Unit Cost Planning functionality (CJ40)

PostPosted: Tue Dec 10, 2013 7:14 am
by Popeye
Hi Folks,

In our implementation project we found an error on Unit Cost Planning functionality (CJ40). Inconsistencies occur when we input multiple currency cost plan under the same WBS and Planning Version.

We’ve also raised issue to OSS for some defects related to this multiple currency which has been replied by SAP.
In the reply, it is stated that the current system behavior is wrong and SAP cannot accommodate it.

Multiple currency cost plan functionality is critical for our business. Anyone could share any workarround or experience on this case?

Regards,
Popeye