Error on Unit Cost Planning functionality (CJ40)

Logistics : PS

Moderators: Snowy, thx4allthefish

Error on Unit Cost Planning functionality (CJ40)

Postby Popeye » Tue Dec 10, 2013 7:14 am

Hi Folks,

In our implementation project we found an error on Unit Cost Planning functionality (CJ40). Inconsistencies occur when we input multiple currency cost plan under the same WBS and Planning Version.

We’ve also raised issue to OSS for some defects related to this multiple currency which has been replied by SAP.
In the reply, it is stated that the current system behavior is wrong and SAP cannot accommodate it.

Multiple currency cost plan functionality is critical for our business. Anyone could share any workarround or experience on this case?

Regards,
Popeye
Popeye
Popeye
 
Posts: 11
Joined: Mon May 26, 2003 2:48 am
Location: Jakarta

Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 4 guests





This website is not affiliated with, sponsored by, or approved by SAP AG.