Issue of plant stock to a non-valuated project

PostPosted: Tue May 21, 2013 6:04 am
by nsr001
Hi PS gurus,
I'm a MM guy and wanted to know how a non-valuated project gets hits with costs when we issue some plant stock (having a value) to a non-valuated project. As you know, there is no accounting document created but on our system I can see a profit center and controlling document getting generated. Does the WBS profit center gets debited and material profit center gets credited? I don't see costs appearing in CJI3... So how does the project accounts for these costs? via profit center only... Please could somebody explain simple terms.

Cheers,
N.

Re: Issue of plant stock to a non-valuated project

PostPosted: Mon Jun 24, 2013 3:50 am
by Amber_Sapper
Hi your Plant stock is non-valuated also?

We have valuated Plant stock and non-valuated project stock so an accounting doc. is created when issuing from Plant to Project stock.

Regards

Re: Issue of plant stock to a non-valuated project

PostPosted: Sun Nov 30, 2014 5:17 am
by shareeq
If your Plant Stock has value , Accounting document will be created .

Regards,