Project Network Activity confirmation based on the actual ti

Logistics : PS

Moderators: Snowy, thx4allthefish

Project Network Activity confirmation based on the actual ti

Postby Popeye » Wed May 15, 2013 3:09 am

Dear all,

I have a client who would like to perform Project Network Activity confirmation based on the actual times (i.e. 12:00 until 15:00).
I try to dig up the PS configuration and found an enhancement so called CONFPS01 PS confirmation: Determine customer specific default values with Function Module EXIT_SAPLCORF_006 PS confirmation: Set default values particular customer.
But I cannot dig deeper information about the function of this enhancement because my limited knowledge in ABAP coding.
Should this enhancement can be used to meet the requirement?
Any one of you have experience in using this enhancement before?

Regards,
Popeye
Popeye
Popeye
 
Posts: 11
Joined: Mon May 26, 2003 2:48 am
Location: Jakarta

Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 2 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.