Project data changes & PR release date

Logistics : PS

Moderators: Snowy, thx4allthefish

Project data changes & PR release date

Postby saplearner12 » Mon Aug 06, 2012 11:59 am

Hi all,

I have a PR that is assigned to my project network.

I am aware that any changes in the basic date, after scheduling of project, could lead to a update in PR delivery date and PR release date.

Does anyone knows why a change settlement rule (from PER to FUL) in level one WBS, after scheduling of project, also will cause a change in the PR release date?

What are the possible changes in project beside changing basic dates, could lead to new update in the PR release date?

Thanks.