Postby sappsmm » Tue Jul 10, 2012 2:29 pm

Hello All

Could you please share your experience how to handle following situation during Data Migration

We use to create separate Projects for Customer Build of samples.

Now business wants to incorporate these projects in already existing R&D Projects under it's own level 1.

Existing situation

R-1000 R&D Project
R-1000-1000 Level 1 WBS for R&D Cost
R-1000-1001 Level 2 WBS (Acct Assignment Elem)

S-1000 Sample Project
S-1000-1000 Level 1 WBS
S-1000-1001 Level 2 WBS (Acct Assigned, Billing Element) Result Analysis Key

Desired Proj Structure

R-1000 R&D Project
R-1000-1000 Level 1 WBS for R&D Cost
R-1000-1001 Level 2 WBS (Acct Assignment Elem)

R-2000-2000 Level 1 WBS for Samples
R-2000-2001 Level 2 WBS (Acct Assigned, Billing Element) Result Analysis Key

For open projects, we want to migrate values (cost / revenues) from S-1000-1001 Level 2 WBS to R-2000-2001 Level 2 WBS

There is RA data from curr yr and past yrs, how do we migrate RA data. If we move existing cost/revenues as Statistical posting, these are not considered in RA of new WBS.

Any suggestion will be highly appreciated.

Thanks
sappsmm
 
Posts: 21
Joined: Thu Mar 20, 2003 3:42 pm
Location: Toronto, Canada

Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 3 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.