Automatic release of succesor activity

Logistics : PS

Moderators: Snowy, thx4allthefish

Automatic release of succesor activity

Postby srini31 » Tue May 08, 2012 3:01 pm

Hello,

We want to automatically the successor activity when the predecessor is marked completed.

Suppose we have 2 activities

10 (with FS)
20 (successor of 10)

When we mark activity 10 as completed, then activity 20 should get released automatically.

We know this can be done via the milestone function 'release following activities'; but is there another way, because then too many milestones get defined (and our activities are in range of 5000)

Thank you,
srini31
 
Posts: 1
Joined: Tue May 08, 2012 2:47 pm

Re: Automatic release of succesor activity

Postby EmptyBrain » Thu May 24, 2012 2:22 am

use "release up to stop indicator" in the milestone functions that will release all the activities until you define another milestone to stop the the releasing of activities.
EmptyBrain
 
Posts: 2
Joined: Wed May 23, 2012 7:29 am


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 3 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.