Change the project definition of a WBS element

Logistics : PS

Moderators: Snowy, thx4allthefish

Change the project definition of a WBS element

Postby bienzo » Mon Apr 23, 2012 5:36 am

Hi!

I need to move some WBS element from a Project Definition to another Project Definition. These WBS element already have plan and actual costs, but they don't have budget.

I think there is no a standard way to move WBS elements form one project to another. ¿Does any one know?

The only way I see is by updating field Project in tables PRPS, PRTE, PRHI and VSPRPS_CN

Thank you in advance

Regards
bienzo
 
Posts: 65
Joined: Sat Apr 21, 2007 12:28 pm