Hi
We went live to control maintenance costs via PS WBS Elements.
Budget Profile is of activation Type : 1 ( automatic) and Annual Values.
Created new Project profile assigned to the Above Budg profile.
Problem :
After Assigning Original Budgets in CJ30, Project/WBSs are not getting AVAC System Status, Their by
system allowing Overrun
What is to be done to set it right, Some WBS with Zero budget assigned already over run in the production system
Thanks in advance