Is there any possibility set to CRTD for newly added WBS?

Logistics : PS

Moderators: Snowy, thx4allthefish

Is there any possibility set to CRTD for newly added WBS?

Postby ramalingeswar on Tue Jan 03, 2012 4:00 pm

Hi Experts,

We are adding new WBS Elements in already released project. As per the standard functionality system is going to set the system status to REL for newly added WBS Elements also, if the project definition was in Released status. Is there any way to set the system status “CRTD” instead of “REL” for newly added WBS Elements?

Please give solution.


Thanks in advance.
Ram

ramalingeswar
 
Posts: 15
Joined: Thu Mar 30, 2006 11:09 pm

Re: Is there any possibility set to CRTD for newly added WBS?

Postby mrshogue on Tue Jul 17, 2012 1:56 pm

We encountered the same problem and a consultant at ASUG recommended we set the Project Definition and Level 1 WBS as PREL. We manually release the Level 2 WBS elements, so when we add additional Level 2 WBS it looks to the Level 1 WBS, which is in PREL status, and sets the status of CRTD on the new WBS. I hope this makes sense. But it works great for us. We did testing and found no financial roadblocks to setting out Project def and Level 1 WBS as PREL.
mrshogue
 
Posts: 3
Joined: Tue Jul 07, 2009 10:39 am