We want Projects to be automatically Closed 60 days after status TECO is at the project.
We have had a background job including a recording in CJ2B where CLSD are set at all objects in the project (project definition, WBS-elements, network, activities and activity elements). This recording can no longer be executed in background (but OK in dialog). We need a new solution.
A recording doing the same in CJ20N does not work
CJ02 can set CLSD at Project definition and WBS-elements - but not at network and activities
CJ20 can set CLSD at all objects in the project except Project definition (should'nt is be possible to set status CLSD at Project definition in CJ20)?
A function module only set status at Project definition and do not respect warnings and errors preventing CLSD to be set (example if the project is not settled).
Can anyone help suggesting what we can do?
Thank you in advance

Lone