Results analysis-Method -03- plan rev and costs added up?

Logistics : PS

Moderators: Snowy, thx4allthefish

Results analysis-Method -03- plan rev and costs added up?

Postby charan1 » Sun Mar 20, 2011 11:18 am

hi,

We use cost based POC method for RA for customer projects. Configuration is standard SAP configuration with no enhancements or custom code. We are on ECC 6 EHP4.

We did cost planning by cost element and by period and revenue planning by revenue element and period using CJR2 in CO version. The CO version in assigned in RA configuration.

When we run RA for a project , it shows planned revenues and planned costs properly. POC and revenue affecting net income are correct.

However , in planned profit/loss , it adds planned revenue with planned costs instead of showing the difference between planned revenues and planned costs.


Please throw some light on what could have gone wrong?
Rgds,
Charan
charan1
 
Posts: 85
Joined: Wed May 23, 2007 2:57 am

Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 4 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.