Able to use unbudgeted WBS in MRP

Logistics : PS

Moderators: Snowy, thx4allthefish

Able to use unbudgeted WBS in MRP

Postby psteam » Mon Dec 13, 2010 3:26 am

Hi all,
I ll try to explain scenario briefly,
â–²WBS A
---â–² Wbs 1
---â–² Wbs 2
---â–² Wbs 3
------●Meterial 3
.
Availability control is active. WBS A is budgeted. WBS 1,2,3 is not budgeted. Meterial 3 is assigned to Wbs 3. We want to operate MRP for this meterial. After executing md51 and md04 the PR is formed according to Wbs 3. However, at PO stage it stops us because it has no budget. So what we need to do is, able to use WBS A‘s budget in this context. How can we overcome this problem?
Is there any way to achive this functional?

Thanks in advance
Regards,
psteam
 
Posts: 2
Joined: Sun Dec 12, 2010 11:55 am

Re: Able to use unbudgeted WBS in MRP

Postby Kadootty » Tue Aug 09, 2011 12:10 am

If you do not maintain any budget on ..
--â–² Wbs 1
---â–² Wbs 2 and
---â–² Wbs 3
then you can utilize WBS A's budget.
Kadootty
 
Posts: 332
Joined: Mon Jul 24, 2006 1:50 am
Location: Dubai