Postby jdc » Wed Sep 22, 2010 7:51 pm

Greetings Gurus,

I am looking for a little SAP (the company) logic.

If I plan costs in CJ40, using annual values (e.g. standard planning profile 000001), the planned costs WILL show in CN41N.
If I plan costs in CJ40, using overall values (e.g. standard planning profile 000002), the planned costs Will NOT show in CN41N.

What the ……..?

So, SAP (the company) thinks that if you plan costs using overall values, you must not be interested in viewing planned costs?

The config behind both profiles is exactly the same except for the Total Values/Annual Values tick boxes.
Am I just missing something here?
jdc
 
Posts: 88
Joined: Sun Apr 18, 2004 6:02 pm

Re: CJ40 and CN41n

Postby Sapimplementer » Sat Oct 02, 2010 7:30 am

I'm thinking CJ9FS to copy the project costs - but not totally sure.
Sapimplementer
 
Posts: 55
Joined: Sat May 08, 2004 6:29 am

Re: CJ40 and CN41n

Postby jdc » Fri Oct 29, 2010 2:14 am

Greetings Sapimplementer,

I played around with CJ9FS (and the other CJ9xx t-codes). It appears as though costs can be copied from one version to another version and/or from one fiscal period to another fiscal period but not from an annual cost plan to an overall cost plan.

We would VERY much prefer to enter only an "overall" plan but..... "overall" plans do not seem to be visible in CJ41N.
It would seem that, since CJ41N is the main structure report, costs would be visible regardless of whether the costs were planned on an overall or annual basis.

Thanks for the direction and feel free to express any other ideas you have.

JDC
jdc
 
Posts: 88
Joined: Sun Apr 18, 2004 6:02 pm

Re: CJ40 and CN41n

Postby greed » Mon Nov 01, 2010 5:47 am

148971 - Planned values in Project Information System
greed
 
Posts: 244
Joined: Wed Sep 28, 2005 8:34 am
Location: Mother Russia

Re: CJ40 and CN41n

Postby jdc » Tue Nov 02, 2010 12:50 am

Hmmm…..
By installing note 106823, “only the total of the years (annual cost planning) is displayed”.
So….
In all of SAP’s infinite wisdom, they made a portion of the structure reports useless for companies wanting to use overall planning.

(SAP seems to be saying…”You can have it anyway you want it (as long as you want it the same way we want it.”)
jdc
 
Posts: 88
Joined: Sun Apr 18, 2004 6:02 pm


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 6 guests





This website is not affiliated with, sponsored by, or approved by SAP AG.