Hi PS Gurus;

We implement PS module with a complete functionalities (WBS, Network, Cost/resources/schedule/materials Planning, Billing, Earned Value, etc.). On go-live phase, we expect to have some ongoing projects that need to be maintained in SAP including their historical data in order to calculate Progress and Milestone billing.

As you know, during project execution, PS is highly depended on other module such as MM, FI/CO, HR, PM. The problem is during cutover, other modules just upload their initial balance into SAP productive system. Thus, we don't get historical data for ongoing project.

I really appreciate if anybody would like to share their experience in cutover strategy for PS.

Regards;
Sy Syarien

sy-subrc = 0
ssyarien
 
Posts: 143
Joined: Tue Apr 11, 2006 9:20 pm
Location: Devastated Place

Re: On going project cutover strategy

Postby Sapimplementer » Sat Oct 02, 2010 7:36 am

All implementations I have seen - actual values are cut across as a lump sum.

The historical data is extracted out of legacy and is availableas a flat fiel. It you have a reporting tool ie BW/Bi you could build this in
Sapimplementer
 
Posts: 55
Joined: Sat May 08, 2004 6:29 am

Re: On going project cutover strategy

Postby Chandrashekhar G Mane » Sun Oct 24, 2010 7:51 am

Create a parallel PS structure consisting of Offsetting Projects, Ofsetting WBS elements at both level. Post the Historical costs on the Offsetting Project Structures. You should be able to get the info ure looking..
Thanks,

Chandrashekhar Mane PMP®
SAP Certified Solution Consultant - Order Fulfillment,Customer Service & Plant Maintenance Modules
SAP Certified Application Associate - CRM Internet Sales with mySAP CRM 2005
Chandrashekhar G Mane
 
Posts: 336
Joined: Wed May 25, 2005 7:02 am
Location: Southbury, CT


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 5 guests



cron


loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.