Postby vdmron » Thu Jun 17, 2010 6:31 am

Hi All

My client would like to set up "Lights Out Machining" in the PS/CATS modules. Basically what they have is one person who is working on two jobs. The employee is watching a machine that can process to jobs at one time. So for each job, it would take 8 hours each if they were done separately, but since both are running at the same time, the employee books 4 hours to each job to make up his/her time. The employee is paid correctly because all of his/her hours are accounted for, but the jobs do not reflect the actual hours taken, because they should each have 8 hours. Has anyone done something similar to this, and if so, what was your solution.

Thanks In Advance
Ron VanDerMaarel
vdmron
 
Posts: 50
Joined: Fri Apr 04, 2003 8:53 am

Re: Lights Out Machining

Postby sappsmm » Tue Sep 27, 2011 8:52 am

We created Dummy Emp Numbers for machines and captured Machine time and transferred cost (based on Cost center/Act Rate) to project
sappsmm
 
Posts: 21
Joined: Thu Mar 20, 2003 3:42 pm
Location: Toronto, Canada


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 3 guests





This website is not affiliated with, sponsored by, or approved by SAP AG.