Postby bennygo » Sun Apr 27, 2008 5:16 am

Hi all
I'm trying to plan workforce in network activities in CMP9.
Although the activities are planned, an error message accepted "No requirements were found for the selection criteria".

Thanks for help.
bennygo
 
Posts: 12
Joined: Wed Mar 12, 2008 9:23 am

Re: Workforce planning

Postby siw2 » Mon Apr 28, 2008 9:38 am

Do the activities have a normal duration?

Can you see them in CMP2/CMP3

If I remember correctly they won't appear in CMP* t-codes unless there is a Normal Duration on tha Activity

Also do the dates sit within the Worforce Planning Profile

Steve
siw2
 
Posts: 308
Joined: Fri Oct 29, 2004 4:16 am

Re: Workforce planning

Postby bennygo » Tue Apr 29, 2008 2:33 am

steve,

Thank you for your answer.
It seems that the reason is configuration of the work center.

Thank you again

Benny
bennygo
 
Posts: 12
Joined: Wed Mar 12, 2008 9:23 am

Re: Workforce planning

Postby flyawayzl » Mon Oct 24, 2011 5:57 am

hi everybody

i have a problem about cmp2 ,when select a activity and want to assign the person to it ,but the person's validity date is not include the period of the activity ,can anybody tell me where the validity date are from ,i have check the personal master data and the project data(wbs,network,activity). thanks
flyawayzl
 
Posts: 2
Joined: Mon Oct 24, 2011 5:44 am


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 4 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.