reverse confirmation MCNF status

Post by Sachu » Fri Sep 28, 2007 5:23 pm

Please let me know how do I reverse the confirmation status MCNF. I tried CN29 but is not working.. The PM accidentally set the status or it was done by an external load, they don't know. When they try to clear the actual finish date it is giving her an error. Has anybody encountered the reversal of MCNF situation. FYI - I tried the confirmation in PBlder also, but it is not wokring. Any insights would help. Thanks!

siw2
Posts: 308
Joined: Fri Oct 29, 2004 4:16 am

Post by siw2 » Thu Nov 01, 2007 4:47 am

Sachu

Are you talking about MCNF on a Network Activity, Network Header or WBS element

MCNF is set whenever a manual confirmation is performed

You will need to reverse this manual confirmation within the PM order. I'm not familar with the PM transactions but suspect they have a simialr t-code as PS's CN29

Let me know how you get on

Steve