Multilevel Budget control

Logistics : PS

Moderators: Snowy, thx4allthefish

Multilevel Budget control

Postby thomasq » Sat Nov 02, 2002 7:19 am

Dear all,

My client want the two level budget control for project. The tolerance limt for super-wbs elements is 10% but for other wbs elements is 5%.

As I check in the system, the budget profile is assigned to project definition not to each wbs elements.

Do you have any good idea in this problem? Thanks in advance

Thomas
thomasq
 
Posts: 29
Joined: Sat Nov 02, 2002 7:14 am

Postby Elton » Tue Nov 05, 2002 1:24 pm

Hi Thomasq

Just an idea :

Considering : tolerance limit equal 10% ; A is current budget to the super WBS elements; B is current budget to the others WBS elements.

1) Release 100 % of the budget to the super wbs elements (A).

2) Release N % of the budget to the others wbs elements (B).

where, N % multiplied by 1,1 should be equal B multiplied by 1,05.

Hope this idea helps.

Good luck, Élton.
Elton
 
Posts: 48
Joined: Mon Oct 21, 2002 11:30 am

Postby thomasq » Wed Nov 06, 2002 12:53 am

Thanks
thomasq
 
Posts: 29
Joined: Sat Nov 02, 2002 7:14 am


Return to Logistics PS

Who is online

Users browsing this forum: No registered users and 2 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.