Postby Csaba » Mon Oct 21, 2002 11:09 am

I can make a cost plan by entering work hours in internal activities and prices in components assigned to an activity. Then I total up to all levels of the structure. Thus, I have a cost plan for activity, network, WBS element.
When it is turned to the budget, I go top-down. But, I see no way to distribute the budget of a WBS element among the networks it has, nor to distribute the budget of the network (if it exists at all) among its activities.
It is possible at all to distribute the WBS element's budget to networks and then to activities? If yes, how?
Csaba
 
Posts: 41
Joined: Mon Oct 21, 2002 10:57 am
Location: Hungary

Postby Guillermo » Mon Oct 21, 2002 11:35 am

Hi Csaba

You can´t distribute the budget of WBS elements in has networks and activities because PS don´t has a budget for networks or activities, its has only cost planning.

The budget is only for WBS elements and is used in availability control.

Greetings.
Guillermo
 