by MikeC » Thu Dec 19, 2002 9:18 pm
Hi
I have planned cost in a project system (which mainly comes from the schedule time for each WBS with activity type)
but it seems that the planned cost keeps on increasing as time goes.
One possibility i know is someone could have changed the planned schedule time.
Any other causes to this changing planned cost ????
regards
MikeC
PS. the actual would come from comfiming thru time sheet
-
MikeC
-
by saching » Thu Dec 26, 2002 1:59 am
May be there are certain overheads or interests costs that would have been defined in the profile that keep on adding as planned costs
Sachin
-
saching
-
by Dadic » Fri Jan 03, 2003 7:20 am
If there is a network assigned to WBS, activity costs are automatically added to manually planned costs of WBS. If you add a new component to network activity, planned costs of assigned WBS will be increased.

-
Dadic
-