LP delivery from project

Post by akrason » Tue May 05, 2020 3:30 pm

Hi,

I have an issue with delivering from project.

I dispose of S/4HANA 1809 without Best Practice scenario installed for PS module. Thus no relevant IMG settings.

So, I have completed (ECC6 as reference model) missing LP delivery type (hard coded?). But also missing sales document type DL (why so? also hard coded?) related SD settings (item category, copying rule).

I am not sure to be either exhaustive or just in my try&test attempts (no previous and specific setting up experience for PS but my SD expertise is o.k.).

Especially that I am still facing error log in CNS0 (message VL321) . Apparently it considers "blank" item category as it states : "Item category is not defined".

What am I missing here?
Andrzej