Order completion date comes from planned finish date

PostPosted: Thu Feb 25, 2016 3:14 am
by PWNeiss
Hi Gurus,
we are facing Problems, when we compete an Inspection Lot, Origin 14 with Usage Decision OK and Standard-follow-up Action QM_PM. This will set the Order status to TECO, but the completion date is not the Usage Decision date, but the planned finish date on the Order.
To have a proper planning, we need the Usage Decision date as completion date. This happens on different settings in Maintenance Plan, time-based, key-date based, always the same Result.
Does anybody know, if there is a Customizing- or Master data setting, which transfers the Usage Decision date as completion date?
Many thanks for your ideas, regards

Paul

Re: Order completion date comes from planned finish date

PostPosted: Wed Jul 13, 2016 1:52 am
by ramesh_kala
Dear Paul,

Spro-->Plant Maintenance and Customer Service--> Maintenance and Service Processing--> Define Proposed Reference Time for Technical Completion--> Set it as Todays Date ( Blank) instead of 2 ,
(I assume follow-up function calling for teco date and inspection lot UD dates both same in your case)

Thanks
Ramesh