Postby neto1a » Wed Sep 09, 2015 8:38 am

Hello, i need to do a maintenance plan that manages order twice a year. One order in January, another in June, only those two dates. Is there some possibility to do this?
neto1a
 
Posts: 11
Joined: Thu Sep 05, 2013 9:26 am

Re: Schedule with specific date

Postby psixalos » Fri Nov 13, 2015 8:49 am

Dear Neto1a,
you could create a calendar of yours where only those 2 months are active. So you will schedulle it to create orders only at these months.
Another option to use the function key date and to create a single cycle plan with every 6 months cycle and if you schedulle it with key date 6 months before the plan will produce 1 order every desired month.
psixalos
 
Posts: 48
Joined: Fri Mar 06, 2009 3:48 am


Return to Logistics PM

Who is online

Users browsing this forum: No registered users and 3 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.