PM Notification Execution Dates

Logistics : PM and its sub-modules & SM

Moderators: Snowy, thx4allthefish, PJA

PM Notification Execution Dates

Postby Lee1706 » Fri Aug 14, 2015 7:31 am

Hi guys

I'm hoping someone can help me. We have a requirement whereby if the notification/service order Req. Start date is changed, the required end date updates accordingly.

Currently the Req. Start date defaults to today's date with the required end date populated according to the settings in OIO2. In some instances the Req. start needs to be amended. When the Req. start date is updated the Required end should be updated automatically, currently this does not happen.

Is there a way to resolve this? Example as follows:

Currently req. Start date = 14.08.2015 system populates Required end date of 17.08.2015.

Update start date manually to 17.08.2015 and required end date remains 17.08.2015 - This needs to update to 18.08.2015 but it doesn't.

How can I make this happen? I cannot be the only person to have come across this issue so I hope someone can help.

Thanks a lot

Lee
Lee1706
 
Posts: 46
Joined: Tue Mar 19, 2013 4:18 am

Re: PM Notification Execution Dates

Postby Lee1706 » Tue Sep 29, 2015 5:49 am

does no one have any suggestion to this issue?
Lee1706
 
Posts: 46
Joined: Tue Mar 19, 2013 4:18 am

Re: PM Notification Execution Dates

Postby theChiel » Tue Sep 29, 2015 12:12 pm

Typically you would manage this via a user exit or BADI enhancement spot. Read the existing start / end dates from VIQMEL, calculate the difference between the current start and the start from the saved image and add that to the end date.
What do you mean there's no undo !!!
theChiel
 
Posts: 304
Joined: Mon Feb 23, 2004 10:30 pm
Location: US of A via ALBA


Return to Logistics PM

Who is online

Users browsing this forum: No registered users and 3 guests





This website is not affiliated with, sponsored by, or approved by SAP AG.