Postby hayls_b » Mon Nov 10, 2014 12:40 am

Hi experts,

I have a maintenance plan scheduling a maintenance work order daily (don't ask!). The Basic start and end times are generating perfectly within the work order when i schedule the plan. However, both Basic Start and Finish times are "00:00".

The Task List assocaited to the Plan is for 4 hours. But appears not to be considered.
The Priority is sent from the Item - but again, is not influencing the times.
The Main & Operational Work Centers have a capacity from 08:00:00 - 17:00:00 but also dont appear to influence the times.

Any suggestions?

HB
hayls_b
 
Posts: 51
Joined: Fri Jul 15, 2005 11:21 am

Re: Influence the Basic Start/Finish Times from a Maint Plan

Postby psquare » Mon Nov 10, 2014 3:44 am

Hi,

The maintenance plan is used to generate workitems like Orders. The influence of the amount of time(like duration) and the capacity are considered in the scheduling programs like trx CM33.

You won't get proposed time from the plan, only the dates on which the order is triggered due to the settings of the plan.

Regards,

P
psquare
 
Posts: 240
Joined: Tue Aug 14, 2007 7:45 am


Return to Logistics PM

Who is online

Users browsing this forum: Yahoo [Bot] and 6 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.