operation capacity load

PostPosted: Sat Aug 02, 2014 10:41 am
by theChiel
I'd like to see the detailed daily schedule for a particular order operation. Say I have an operation planned for one person 16 hours, the work center has 7.5 working hours with 15 minutes of breaks and the factory calendar has Saturday, Sunday and every other Friday off. If the operation is schedule to start Thursday it's going to end sometime Monday/Tuesday the following week. Can anyone point me towards the function modules and / or tables the daily capacity commitment of the operation is stored.


Thanks

Re: operation capacity load

PostPosted: Mon Aug 04, 2014 1:34 am
by PJA
Try table KBED.

AFKO-BEDID -> KBED-BEDID
of
AFVC-BEDID -> KBED-BEDID

Re: operation capacity load

PostPosted: Wed Aug 06, 2014 2:08 pm
by theChiel
Thanks Pete

I tried KBED but it only shows the AFVC/AFVV data ... the start date and the number of hours not how the hours may be distributed over days for a duration > work center shift.


Stewart

Re: operation capacity load

PostPosted: Thu Aug 07, 2014 1:54 am
by PJA
Stewart,

I might have time later to have a look.

In the mean time, have a look at Package "CX" via se80, specifically at the various function groups/modules.