Next Planned Date is different in IP10 and IP24 for same maintenance plan.
How to make them aligned? I have already tried scheduling using command IP30 and it didn’t work.
Example:
Maint Plan: INS-001-1128 6M PM
IP10 shows next PM on 22.09.2014 (6M after 10.03.2014 actual completion date)
IP24 shows next planned date is 26.06.2014