FAQ: Manual Cut-Over Activities

Post by PJA » Mon Jun 01, 2009 3:51 am

FAQ: Cut-over Activities

- Selection screen variants (e.g. IW38)
- Report display variants (e.g. IW38)
- Strategies for maintenance plans
- Number ranges (manual transports)
- Data for non-customisable Z tables
- Quickview/ABAP Query reports
- Transfer open orders/notifications from legacy system to SAP
- Schedule maintenance plans from start-date of go-live
- Classes & Characterisitics (you can ALE these from one system to another)
- Schedule background jobs (e.g. IP30, custom developed reports/programs, etc)
- SmartForm fonts

michalis12
Posts: 395
Joined: Tue Aug 09, 2005 9:32 am
Location: Athens, Greece
Contact:

Re: FAQ: Manual Cut-Over Activities

Post by michalis12 » Mon Jun 01, 2009 9:40 am

Classification, ex. characteristics for measurement documents; unless of course you use ALE to "transport" them from one system to the other.

hariharant2000
Posts: 1
Joined: Mon Apr 14, 2008 6:34 am

Re: FAQ: Manual Cut-Over Activities

Post by hariharant2000 » Tue Jun 02, 2009 3:34 am

Hi

-Schedule Background job process for developed programs from Golive date on wards.

Regards

Harris

psquare
Posts: 240
Joined: Tue Aug 14, 2007 7:45 am

Re: FAQ: Manual Cut-Over Activities

Post by psquare » Thu Jun 04, 2009 1:31 am

Inform business for system downtime.

PJA
Posts: 11383
Joined: Sun Jul 20, 2003 3:11 pm
Location: Deepest darkest Aberdeenshire
Contact:

Re: FAQ: Manual Cut-Over Activities

Post by PJA » Thu Jun 04, 2009 1:46 am

psquare,

I was more thinking about the tasks we need to perfrom in the system.

Can you eloborate..

PeteA

sanjamantri
Posts: 8
Joined: Wed Apr 26, 2006 11:58 pm

Re: FAQ: Manual Cut-Over Activities

Post by sanjamantri » Wed Jun 17, 2009 4:43 am

The following task can be also done.
1. If any interface is there then update of master data in legacy system and SAP both depending on one way or 2 way interface
2. start date of interface
3.maintaing mapping tables for interface
Regards
sanjay Kumar Mantri

mikejnger
Posts: 18
Joined: Wed Jun 24, 2009 8:05 am

Re: FAQ: Manual Cut-Over Activities

Post by mikejnger » Mon Jul 06, 2009 9:45 am

Machine BOMs not being set up correctly was our main issue

ramesh_kala
Posts: 154
Joined: Sun Aug 31, 2003 7:37 am
Location: Bangalore
Contact:

Re: FAQ: Manual Cut-Over Activities

Post by ramesh_kala » Mon Jul 13, 2009 12:32 am

Hi PJA,

Some points -how to collect/ load historical data - like
i) spares consumption- i could not cover this because of non availiblity of data.
ii) Equipments down time details entry ( IW21- BDC and make file ready for loading these datas).
iii) Check for Non Valuated material codes ( which we are going to use for refurbishment and external repair).
and current stock verification.
iv) Plan masters Due date of maintenance of each tasks based on current schedule list.

Thanks & Regards,

Ramesh Kalammanavar

chidam33
Posts: 28
Joined: Fri Jun 05, 2009 12:02 pm

Re: FAQ: Manual Cut-Over Activities

Post by chidam33 » Fri Aug 21, 2009 11:15 am

OK..

Create Sets
set up batch jobs.

Kris

PJA
Posts: 11383
Joined: Sun Jul 20, 2003 3:11 pm
Location: Deepest darkest Aberdeenshire
Contact:

Re: FAQ: Manual Cut-Over Activities

Post by PJA » Sat Aug 22, 2009 4:47 am

Kris,

Create sets for what???

PeteA

chidam33
Posts: 28
Joined: Fri Jun 05, 2009 12:02 pm

Re: FAQ: Manual Cut-Over Activities

Post by chidam33 » Sat Aug 22, 2009 7:15 am

HI PeteA,

If you have sets determined in any of your enchancements, reportes etc..then we have to manually create sets.

Thanks

Kris

PJA
Posts: 11383
Joined: Sun Jul 20, 2003 3:11 pm
Location: Deepest darkest Aberdeenshire
Contact:

Re: FAQ: Manual Cut-Over Activities

Post by PJA » Sat Aug 22, 2009 9:45 am

Kris,

Sorry, still don't get it...

Where are these sets created?

PeteA

arnaudr
Posts: 21
Joined: Fri Mar 10, 2006 10:07 am
Location: France

Re: FAQ: Manual Cut-Over Activities

Post by arnaudr » Mon Sep 07, 2009 5:28 am

Hi,

I'm not very familiar with ABAP but what i understand a set is a kind of variable refering to a field table for which you can store values, and can be used in programs (ex : you can create a set for PM order type and record some values for which you want to perform a function).
It is created with tcode GS01 (create sets).
Hope it helps,
Arnaud.

hz79hc
Posts: 145
Joined: Fri Feb 07, 2003 3:06 pm

Re: FAQ: Manual Cut-Over Activities

Post by hz79hc » Tue Oct 06, 2009 7:24 am

Does anyone out there load "historical" orders?

The amount & type of data you may require loaded depends on whether you are implementing PM at same time as other modules -- or in a follow-on --- Yes?