by gielpeeters » Thu Jul 24, 2008 9:15 am
Dear all,
When I run transaction IA01 (Create Equipment Task List), and use Copy reference to copy a Task List on an equipment it doesn't copy the Maintenance Package Allocations (or cycles). I would like that these cycles are included in the copying routine. Is there a customizing setting that I am overlooking? Or does anyone know another solutiuon.
Your help is greatly appreciated.
-
gielpeeters
-
- Posts: 18
- Joined: Wed Jan 16, 2008 4:58 am
by gielpeeters » Tue Sep 09, 2008 2:11 am
FYI:
According to SAP this is intended behaviour.
We have solved this problem by using LSMW. The po packages (marks in checkboxes) were found in SAP table PLWP. The inputfile for LSMW was created with this PLWP in combination with EAPL. This way we could do about 90% of the equipment task lists. The remaining was done manually.
-
gielpeeters
-
- Posts: 18
- Joined: Wed Jan 16, 2008 4:58 am
by balanagesh » Thu Apr 12, 2012 12:48 am
Hello There,
Could you please let me know in detail how you prepared the lsmw for this?
I've got this requirement now and hence looking for a solution.
Regards,
Bala.
-
balanagesh
-
- Posts: 1
- Joined: Thu Apr 12, 2012 12:33 am
by PJA » Thu Apr 12, 2012 9:26 am
Locked: Hijacking an old post is against the forum rules.
Please create a new post and refer to any useful material
PeteA
-
PJA
-
- Posts: 10875
- Joined: Sun Jul 20, 2003 3:11 pm
- Location: Deepest darkest Aberdeenshire
-
Return to Logistics PM
Who is online
Users browsing this forum: No registered users and 5 guests