Change Delivery Date in PO?

PostPosted: Mon Oct 02, 2017 2:48 am
by simsa63
Hi,

We have process sales order – purchase requisition – purchase order.
There is need to change purchase order delivery time in some cases.
The problem is that we can change dates to sales order but in purchase order system uses factory calendar.
The need is that we could change dates (EKET_EINDT) also in purchase order (own calendar).
We can’t change factory calendar and we don’t want to change dates for all vendors and for all items with same item category.

So, does anyone know is it possible to change dates for purchase requisition and/or purchase order?
And pr and po are created automatically, so manual change isn't possible.

Any ideas?