Release strategy for PO changes

Postby MartasVolnas » Mon Jan 23, 2017 3:33 am

Hello,

I have a request from users to disable the triggering of release strategy, when the PO value decreases as the PO is already approved for higher value. They only want to trigger the release strategy again if the PO value increases. I tried to manage via Release indicators, but no option fits into the requirement. Based on the SAP Note 662993 the standard SAP logic is to trigger the release strategy always, when the new Release strategy is reached for both ways (PO value increase or decrease). Is there any other way how to handle? Does anybody faced the same?

Thanks in advance for any thoughts.
MartasVolnas
 
Posts: 1
Joined: Tue Jan 17, 2017 4:00 am

Re: Release strategy for PO changes

Postby Ha Tran » Tue Jan 24, 2017 1:08 am

Hi,

The release strategy won't be re-set if the PO value decreases as far as the standard SAP is concerned.

Cheers,
HT
Ha Tran
 
Posts: 28316
Joined: Sun Mar 30, 2003 8:29 pm
Location: Perth, Western Australia


Return to Logistics MM

Who is online

Users browsing this forum: No registered users and 7 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.