Postby Anandj » Mon Dec 05, 2016 7:49 pm

Hello ,
I am confused with how the float time i when running RM07ICN1 through background job .Suppose the float time for
cycle count indicator A (12 times a fiscal year)is defined as 5 days . Assuming if the batch job runs once in day for the plant and if the PI gets
document created on the first due day itself , then there is no use real use for floats days ? Background job is going create the PI document on its
proposed date and hence I am not sure how this float days will influence the grace period .

Thanks in Advance for your immediate response .

with regards ,
AnandJ
Anandj
 
Posts: 210
Joined: Thu Jul 29, 2004 10:03 am

Return to Logistics MM

Who is online

Users browsing this forum: No registered users and 14 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.