PO Order Acknow (AB) vs Ship notes (LA)

Logistics : MM and its sub-modules (WM, IM, PO, LIS)

Moderators: Snowy, thx4allthefish, svetja, Ha Tran

PO Order Acknow (AB) vs Ship notes (LA)

Postby Lauriel » Tue Apr 07, 2015 12:00 pm

Hi everyone,

I check in search and found the same question posted a few years ago without any solution.
Here is my issue:

We are using AB for confirmations of purchase orders In the confirmations tab of purchase orders.
In MD04 this shows as: MRP Element became "ShipNt".

We also use LA for shipnotes. This also shows up ast MRP element ShipNt.

the same MRP element for 2 different confirmations is causing issues with our MRP planners and everyone else looking at MD04. They see that the parts have "shipped" when in fact, what they are looking at is an order acknowledgement with a "maybe" will ship.

I see in SPRO that there is a category for purchase acknowledgements "RU", but this is just a table.


How/where do we show the different MRP Element for 1. Order Confirmation and 2. Shipping Notification?

Thanks
Laurie
Lauriel
 
Posts: 282
Joined: Wed Oct 23, 2002 2:04 pm
Location: Wisconsin

Return to Logistics MM

Who is online

Users browsing this forum: No registered users and 8 guests





This website is not affiliated with, sponsored by, or approved by SAP AG.