Postby Brynarn » Fri Feb 06, 2015 3:21 am

Hi!

We are using mixed storage meaning that A, B and C materials can be placed in the same storage bin.

Example: BIN M4 has one A material, one B material and one C material stored at the bin.

When we run LX26 in order to create physcial inventory document it should only be time for the A material to be counted but in the inventory document all materials in the bin M4 are included, also the B and C material.

Any idea how to get only the materials that there is time for counting based on ABC rules to be included and not all the materials at a bin?

Many thanks in advance!
/B
Brynarn
 
Posts: 85
Joined: Tue Jun 20, 2006 6:30 am

Return to Logistics MM

Who is online

Users browsing this forum: No registered users and 11 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.