"MRP exception message 26:Excess in individual segment --> 1

Postby kurthet » Tue Feb 11, 2014 4:28 pm

Hi, we are running SAP ECC 6.0 and for all our purchase to order sales orders and projects, we are receiving a message in MD04, "MRP exception message 26:Excess in individual segment --> 1.000". The sales order quantity has not been reduced and this is causing confusion for our buyers while they are reviewing as they think they need to cancel. Has anyone else run into this and have a solution?
I did find a post that suggested adding a tick in the 'Requirements transfer' selection against the schedule line category in SD->Basic functions->avail check and transfer of requirements->Transfer of requirements->Define procedure for each schedule line category. Not sure if it is that simple and what other ramifications this tick causes. I'm also told that there is a setting that lets MRP drive the demand for the projects and sales orders instead of the project and sales order driving the demand directly. However, we don't want to lose visibility of the PO on the sales order or slow the process. Appreciate any feedback or suggestions, thanks!
kurthet
 
Posts: 2
Joined: Tue Feb 11, 2014 4:12 pm

Return to Logistics MM

Who is online

Users browsing this forum: Google [Bot], Google Adsense [Bot] and 13 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.