We are currently closing POs (to remove the commitments) by reducing the total amount on the PO to reflect what was received in order to remove any budget commitments. Is there a better way?
For example: We have a Service/limit PO for 100,000 that is against a budget. We have received $80K on that PO and will not need to keep the remaining $20K open and committed to the budget. Normally we would reduce the $100K to $80K and flag the final invoice indicator.
Is there any way to achieve this without having to reduce the $ or quantity commitment on the PO? Like checking an indicator on the PO HDR/or PO line item level to indicate the PO is delivered?
thanks in advance