Hi,
We are looking into possibility to set zero day in PIR planned delivery date, is it possible? If yes, please advise how.
Thanks!
Mysapfans
|
|
This website is not affiliated with, sponsored by, or approved by SAP AG.
Can planned delivery date set to zero day in PIR?Moderators: thx4allthefish, Snowy, Ha Tran, svetja
4 posts
• Page 1 of 1
Can planned delivery date set to zero day in PIR?Hi,
We are looking into possibility to set zero day in PIR planned delivery date, is it possible? If yes, please advise how. Thanks! Mysapfans
Re: Can planned delivery date set to zero day in PIR?Hi,
I don't see any particular reason why this field can't be left as blank in PIR. Have you checked in the configuration if this field was set as mandatory?. If not, then you can leave this field blank during PIR maintenance. Cheers, HT Moderator: http://www.sapfans.com
Re: Can planned delivery date set to zero day in PIR?Thank you, HT, it worked!
Mysapfans
Re: Can planned delivery date set to zero day in PIR?I confirm that no fill is Like 0
Regards
4 posts
• Page 1 of 1
Who is onlineUsers browsing this forum: No registered users and 19 guests |
|