Service Quantity from PReq to PO

Logistics : MM and its sub-modules (WM, IM, PO, LIS)

Moderators: Snowy, thx4allthefish, Ha Tran, svetja

Post Reply
SAPMMLover
Posts: 21
Joined: Wed Mar 09, 2011 11:10 pm

Service Quantity from PReq to PO

Post by SAPMMLover » Fri Oct 28, 2011 8:32 am

Hi,

I have a question that relates to the purchasing of services.

I am able to increase the service quantity on a PO to a value that is greater than what was requested/approved for on the purchase requisition (when converting a service requisition to a PO).

Is there any way to prevent this? I have set the message 06 076 (“Materials of requisition & item & alr. ordered in full”) to an Error but this is relevant only for materials. Is there something similar for services (I read online about message SE 438 (“Quantity & exceeds target quantity & for the purchase req. by &”), however after setting this to an Error, the system still allows me to order more on the PO than what was requested/approved on the Requisition).

Thoughts?

Ha Tran
Posts: 28320
Joined: Sun Mar 30, 2003 8:29 pm
Location: Perth, Western Australia
Contact:

Re: Service Quantity from PReq to PO

Post by Ha Tran » Fri Oct 28, 2011 1:46 pm

Hi,

Which quantity did you refer to?. Was it the PO line item quantity (EKPO-MENGE) or PO service line item quantity (ESLL-MENGE)?

Cheers,
HT

SAPMMLover
Posts: 21
Joined: Wed Mar 09, 2011 11:10 pm

Re: Service Quantity from PReq to PO

Post by SAPMMLover » Fri Oct 28, 2011 2:01 pm

PO service line item quantity (ESLL-MENGE)