I have defined a material which is to be externally procured and while creating a material it asks for checking group in MRP3 view.
What would happen if i specify no availability check(KP) for this externally procured item.Will SAP check while running mRP that there are already planned receipts for this item and will propose a quantity after netting the requirements with KP checing group.
And while issuing it against a production order, there will again be no availability check as it KP.
Does it mean that while creating Requisitions it will not do any availability check and while issues it will do availability check.
I have specified checking group 01 in material master where stock in quality inspection is marked and then moved partial stock from unrestricted to quality stock.In Md04 , only the unrestricted stock was displayed and not the quality stock.Why it should happen like this.
Thanks