Hi Everyone,
When a production run crosses multi days, component material requirements can be evenly distributed by days via distribution key. My question is, is it possible to distribute requirements not just on days, but also on production times (hours)? Say, production runs 1 hour on 10/25, and production runs 20 hours on 10/26. Standard distribution function will put 50% requirements on 10/25, 10/26 evenly. Has anybody got the same issue? Any workaround?
Thanks in advance.
Yimin