Hi,
I have a problem when calculating MRP with the quantitty of open target delivery.
example:
A delivery program with a target quantity of 1000 units.
We have a delivery schedule of 800 units and a good receipt of 1000 units. Open target quantity is 800 units
The MRP takes into account the open target quantity and believes that you can still order 200 units as we have already received the full scheduling agreement.
How to make the MRP takes into account the quantity delivery and not open target quantity?
Or can we ensure that the open target quantity = delivered quantity?
Bests regards