Hi all,
In make to order process, when i convert planned order to production order, the related SO item's status will change to 'AO02 Do availability check' automatically.
Can anybody tell me what is mean of this status?
thanks in advance,
EP
|
|
This website is not affiliated with, sponsored by, or approved by SAP AG.
Status: AO02 Do availability checkModerators: thx4allthefish, Snowy, mike_ac, Lost Identity
1 post
• Page 1 of 1
Status: AO02 Do availability checkHi all,
In make to order process, when i convert planned order to production order, the related SO item's status will change to 'AO02 Do availability check' automatically. Can anybody tell me what is mean of this status? thanks in advance, EP
1 post
• Page 1 of 1