Postby DusanKelle » Thu Sep 18, 2008 9:14 am

Been facing this problem often:
In case the company orders pre-materials from vendors by using schedule line (refering to the scheduling agreement), how one can enter the delivery date confirmation sent by vendor (externally by e-mail)? I mean, if the shipment has been confirmed to be deliverd later than requested, so far the pre-material disponent changes the delivery date of the schedule line manually. By doing this, however, he loses the original delivery date in the system. The thing is, that disponent has to do this if he wants the availability check (when planning the production) to be up-to-date and the availability check calculates with real dates.
On the other hand, if doing all this, Purchasing cannot use the standard tool for evaluating the on-time delivery (t-code MC$6).

Thank you all for all of your helping (or at leats encouraging :) ) posts.
DusanKelle
 
Posts: 1
Joined: Thu Sep 18, 2008 9:04 am
Location: Slovakia

Return to SRM Supplier Relationship Management

Who is online

Users browsing this forum: No registered users and 4 guests





loading...


This website is not affiliated with, sponsored by, or approved by SAP AG.