DMRs for parallel production

PostPosted: Wed Nov 18, 2015 7:29 am
by aat99aat99
Hi

We are producing the same material on 2 different lines, and we have DMRs set up against the characteristics on the inspection plan for this material.

Is there anyway how we can keep the DMR rules in step between the 2 lines as we don't want the creation of an inspection lot on one line affecting the skipping/non skipping of the characteristics on the other line when there is a GR done

I had thought of copy the relevant chars so there would be a copy of the original on LINE A for LINE B, but are there any better ways ?

Regards

Alistair