Page 1 of 1

Convert DP Planned Order to PPDS Planned Order

PostPosted: Wed Mar 17, 2004 4:06 am
by Guest
Hi,
I've cretaed an integration model to transfer Planned Orders from APO to R/3. When I create an SNP Planned Order the data transferred to R/3 is the same as in APO, but when I convert the SNP order to a PPDS order the dates transferred to R/3 is not the same as in APO.
I've checked if there are user-exits in order to solve this, but I only found user-exits in R/3:
- EXIT_SAPLCORD_004
- EXIT_SAPLCORD_005
Using these user exit I was not able to change any date. Does anyone know ho to use these user exits and is there is any other one from APO?

Thanks in advance,

Joan

Re: Convert DP Planned Order to PPDS Planned Order

PostPosted: Mon Sep 17, 2012 7:55 pm
by geoffreyboy
Same question.

Re: Convert DP Planned Order to PPDS Planned Order

PostPosted: Fri Nov 02, 2012 1:00 am
by apo klaus
Hi Joan,

if planned orders have diffenrent dates in APO and in R/3
you might check the basic settings

Material master:
float after production
float before production
should both be set to zero

Customizing:
you have to deactivate "scheduling" of planned orders
to see APO dates in R/3

Rgds Klaus